Jonesboro Storm Shelters(870) 604-3141

Not every "storm shelter" is built to the same bar. There are real standards, and a good installer can show you that their product meets them.

What makes it a FEMA safe room: the documents

What they require for a home tornado shelter

Storm shelter doors: what to check

The door is the weak point of most shelters, and it's where buyers get fooled most often. FEMA's homeowner guide spends a whole section on it (FEMA P-320, section 3.9, plus the Residential Tornado Safe Room Doors fact sheet in its Appendix B). The short version:

What to ask for: the test certification or the third-party label (UL is one lab that labels them) showing the door assembly passed ICC 500 testing for 250 mph, and written confirmation that the hardware being installed is identical to the hardware that was tested. Texas Tech's wind lab and UL both keep lists of door products that passed. Prefab shelters usually come with a door tested as part of the unit; a site-built room or a closet conversion is where you need to check hardest. Bring this up when you compare quotes, and see how doors differ across steel, concrete and built-in safe rooms. Already have a shelter with a door that sticks or a part that's gone? See storm shelter door repair and replacement.

Craighead CountyTalk to us about a shelter

(870) 604-3141

Listed and labeled: the 2024 rule that changes the paperwork

Under the 2021 and 2024 International Residential Code and ICC 500-2023, every residential storm shelter needs construction documents signed and sealed by a registered design professional with its permit application, unless it's a prefabricated unit that is listed and labeled as meeting ICC 500 (FEMA P-320, 2024 edition, sections 4.2 and 4.2.1). A test report alone no longer gets a prefab unit out of that step. What that means for you:

Who approves a storm shelter in Jonesboro, and what the inspector checks

Code books talk about the "authority having jurisdiction," or AHJ. Inside Jonesboro's city limits that's the City of Jonesboro Inspections Department at 300 S. Church St. (870-933-4602). Its page says the department does plan reviews, enforces the Arkansas Fire Prevention Code on new construction and remodeling, and performs the structural inspections. The codes it lists as in force since January 1, 2023 are the 2021 Arkansas Fire Prevention Code, Volume II (Building) and Volume III (Residential), plus the 2021 Existing Building Code. Those volumes are Arkansas's editions of the 2021 International Building and Residential Codes, so the shelter rules in them are the 2021 ones.

How a home shelter permit moves through City Hall

For storm shelters in Jonesboro, AR outside city limits, in the rest of Craighead County, ask the county judge's office or your installer which office, if any, issues permits where you live before the unit is set.

Buildings in Arkansas that must have a shelter

For most homes a shelter is optional. For some buildings it isn't. When Arkansas moved to the 2021 International Building Code on January 1, 2023, the Arkansas Department of Education reminded school districts (memo FT-23-002, November 2022) that under section 423.5 all Group E occupancies with an occupant load of 50 or more must have a storm shelter built to ICC 500, which applies to new schools, additions and, where applicable, total renovations. The same section of the building code covers 911 call centers, emergency operations centers, and fire, rescue, ambulance and police stations in the 250 mph tornado zone. That is why newer Jonesboro-area school buildings double as safe rooms; which of them open to the public is on our Craighead County public shelter page.

Built to code or built to FEMA's funding criteria?

A shelter only has to meet ICC 500 to pass inspection. A safe room paid for with FEMA hazard mitigation money, which in Arkansas comes through ADEM's hazard mitigation grants, also has to meet the extra criteria FEMA puts in P-361, and the design has to show it meets them before the grant pays. For a homeowner the practical difference is small: a listed and labeled residential unit with a tested door, installed on the documented foundation with the anchors inspected, is what the city will look for. If you're applying for a grant or rebate program, ask before you buy which standard and which paperwork it requires, because a unit installed first and documented later may not qualify.

What the inspector will want to see on site is mostly the paper trail: the listing number or the sealed drawings, the foundation and anchor plan, and, for anchors drilled into an existing slab, the special inspection or the building official's own check of the anchors.

FEMA P-361 residential safe room checklist

Most of the FEMA and ICC 500 questions people search for, like how big, how many vents, how it's anchored and what goes inside, have a short answer buried in a long document. Here they are in one place for a home tornado safe room, from FEMA P-361 (April 2021 edition) and FEMA's December 2024 homeowner guide (FEMA P-320), both of which follow ICC 500-2023.

ItemWhat the criteria sayWhat to ask for
Floor area (occupancy)At least 3 sq ft of usable floor per person in a one- or two-family home; 5 sq ft in other residential buildings (P-361 Table B5-3). Toilets and fixtures don't count as usable area.The rated occupancy on the label or drawings, and whether it covers everyone who'd be home
VentilationNatural ventilation of about 2 sq in per occupant (4 sq in minimum), split between the upper and lower parts of the room; doubled if all intake openings sit 72 in or more above the floor. FEMA's plans list 2 to 11 pipe vents for 1 to 16 people. If mechanical ventilation is used instead, ICC 500 calls for 5 cfm of outdoor air per occupant (P-320 Drawing SR2.2; P-361 B7.2.5).The venting calculation on the drawings, and how the vents are protected from debris
Door assemblyThe door, frame, hinges, latches and anchors tested together for the 250 mph pressure and debris tests, installed exactly as testedThe test report or third-party label for the whole assembly
Anchorage and foundationThe construction documents have to show the minimum foundation (slab thickness, reinforcement, concrete cover) and every anchor. Most existing house slabs weren't designed for safe room loads, so FEMA wants engineering calculations for an existing slab (ICC 500 §106.2; P-361 B1.2.7)The anchor plan and the slab check for your house, not a generic sheet
Special inspectionRequired when anchors are post-installed into hardened concrete or masonry, such as bolting into an existing garage floor. On residential safe rooms it can be skipped only if the building official verifies the foundation and anchoring themselves (P-361 B1.2.7)Who does the inspection, or the city's written OK in its place
Distance from the houseA safe room outside the house has to be within 150 feet of travel from the nearest door of the home (ICC 500, per P-320 §3.6)The walking route, in the dark, in rain
Permit and paperworkSigned and sealed construction documents, unless the prefab unit is listed and labeled to ICC 500 (P-320 §4.2)The listing number, or the engineer's sealed drawings, and the permit
Emergency suppliesFEMA strongly recommends a first aid kit in every residential safe room, because people get hurt rushing in. P-320's kit list for a tornado room: 1 gallon of water per person for a day, a day of food that needs no cooking, a flashlight for every 4 people, a battery or NOAA weather radio, a phone or CB radio with extra batteries, tools to open a damaged door from inside, and medicines (P-320 Appendix B)Room on the floor plan for the kit, so it lives in the shelter

One more line from P-320's Appendix B that belongs on every checklist: register the exact location of the safe room entrance with local officials right after it's built, so responders can dig you out if debris blocks the door. In Jonesboro that's the city's E-911 storm shelter registry. And when the warning sounds, how long you'll likely be in there is on our page about Jonesboro tornado warnings.

Questions to ask any installer

Labels like "FEMA approved" get used loosely. FEMA publishes criteria; it doesn't certify individual products. Ask for the test documentation instead.

Common questions

How many vents does a FEMA residential tornado safe room need?

FEMA P-320 (2024) uses ICC 500-2023: about 2 square inches of natural ventilation per occupant, 4 square inches minimum, split between the upper and lower parts of the room, and doubled if all the intake openings are 72 inches or more above the floor. Its plans call for 2 pipe vents for up to 3 people and 11 for 16 people.

What does ICC 500 compliant mean?

The shelter is designed and tested to the ICC/NSSA 500 standard: for a tornado shelter, 250 mph design winds and resistance to a 15-pound 2x4 debris impact at 100 mph on walls and doors.

Is FEMA P-361 the same as ICC 500?

They're closely linked. ICC 500 is the building-code standard. FEMA P-361 is FEMA's safe room criteria, which build on ICC 500 and reference it for testing, with some additional recommendations.

What does listed and labeled mean for a storm shelter?

An independent certification body has checked the product against ICC 500 and it carries that body's label. Under the 2024 IRC, a prefab shelter that is listed and labeled can be permitted without signed and sealed engineering drawings; one that isn't needs them. FEMA suggests checking the ICC-ES directory for the exact model.

Who inspects and approves a storm shelter in Jonesboro?

Inside city limits, the City of Jonesboro Inspections Department (300 S. Church St., 870-933-4602) is the authority having jurisdiction. Applications start at Planning and Zoning, Engineering checks floodplain issues, and Inspections approves the plans and issues the permit; the city lists a storm shelter permit at $50. The plans need the foundation details, and anchors drilled into an existing slab need a special inspection or the building official's own check.

Does FEMA approve storm shelters?

Not individual products. FEMA publishes design criteria. Manufacturers have their products tested against those criteria. Ask for the test report.

Request a call back

Talk to us about a shelter

Tell us your town, how many people it needs to hold and what kind of shelter you're thinking about, and we'll call you back.

(870) 604-3141

Call nowRequest